Wrexham Roadworks Update: 33 Sets Scheduled Over The Next Week
Very busy week for roadworks with 33 sets scheduled to take place across the county borough!
As usual expect some road closures and diversions across the area while the roadworks take place.
Details of where and when roadworks are taking place between can be found below. If there’s any roadworks we have missed off, then please email [email protected] and we will try our best to chase them up.
_______________________________________________
Smithy Lane, Pentre Bychan Replacement gas main
ROAD CLOSURE
From 03/04/2017 to 10/07/2017 Duration 14 weeks Expected delay N/A
For further info: Wales and West Utilities 01792 326214
_______________________________________________
A528 Overton Nr. Red Hall Lane Lay new water main
2 way traffic lights
From 02/05/2017 to 06/06/2017 Duration 5 weeks Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
Salop Road jct. Oswestry Road & A528 Queensbridge Farm, Overton Lay new water main
3 way traffic lights
From 22/05/2017 to 09/06/2017 Duration 3 weeks Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
Striga Bank, Hanmer Lay new water main
3 way traffic lights
From 15/05/2017 to 07/07/2017 Duration 12 weeks Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
Rossett Road, Commonwood Water Network Repairs
3 way traffic lights
From 02/05/2017 to 24/07/2017 Duration 11 weeks Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
A528 Overton Road, Marchwiel BT Cabling/ Ducting
2 way traffic lights
From 08/05/2017 to 19/05/2017 Duration 12 days Expected delay < 5 mins
For further info: GCN Ltd 01745 331551
_______________________________________________
Clywedog Road North jct Clywedog Road South, Wrexham Industrial Estate BT Cabling/ Ducting
3 way traffic lights
From 11/05/2017 to 22/05/2017 Duration 12 days Expected delay < 5 mins
For further info: GCN Ltd 01745 331551
_______________________________________________
Blue Bell Lane jct. Westbury Drive, Pandy BT Cabling/ Ducting
3 way traffic lights
From 15/05/2017 to 22/05/2017 Duration 8 days Expected delay < 5 mins
For further info: GCN Ltd 01745 331551
_______________________________________________
Llyndir Lane, Broadoak, Rossett Stress test new rail line
ROAD CLOSURE
From 20/05/2017 to 21/05/2017 Duration 1 night Expected delay N/A
For further info: Centurion Services
Be Aware: 21:00 – 06:00hrs
_______________________________________________
Ty Helyg Road, Llwynmawr Overhead Cable Works
ROAD CLOSURE
From 25/05/2017 to 25/05/2017 Duration 1 day Expected delay N/A
For further info: SPEN – 0845 2722424
_______________________________________________
B5445 Marford Hill, Marford Install ducts
2 way traffic lights
From 15/05/2017 to 24/05/2017 Duration 10 days Expected delay < 5 mins
For further info: O’ Connors Utilities
_______________________________________________
Broadoak Level Crossing, Llyndir Lane, Rossett Rail line repairs
ROAD CLOSURE
From 22/05/2017 to 22/05/2017 Duration 1 day Expected delay N/A
For further info: Centurion for Network Rail
_______________________________________________
A5 Froncysyllte Overhead Cable Works
2 way traffic lights
From 22/05/2017 to 22/05/2017 Duration 1 day Expected delay < 5 mins
For further info: Voltcom Construction
Be Aware: 09:30 – 15:30
_______________________________________________
Middle Sontley Road, Erddig BT Cabling/ Ducting
ROAD CLOSURE
From 23/05/2017 to 25/05/2017 Duration 3 days Expected delay N/A
For further info: GCN Ltd 01745 331551
_______________________________________________
B5430 Talwrn Road jct. Heol Offa, Coedpoeth Mains cleaning
3 way traffic lights
From 24/05/2017 to 27/05/2017 Duration 3 nights Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
Be Aware: night time works only
_______________________________________________
Pentre Fron Road, Coedpoeth Mains cleaning
ROAD CLOSURE
From 24/05/2017 to 25/05/2017 Duration 1 night Expected delay N/A
For further info: Dee Valley Water 01978 846946
Be Aware: Night time closure
_______________________________________________
Smithy Lane jct. Windermere Drive, Wrexham Virgin Media – Cabling Works
3 way traffic lights
From 19/05/2017 to 23/05/2017 Duration 5 days Expected delay < 5 mins
For further info: Actavo for Virgin Media
_______________________________________________
Mile Barn Road jct. Lichfield Close/Cosford Close, Wrexham Virgin Media – Cabling Works
3 way traffic lights
From 21/05/2017 to 22/05/2017 Duration 2 days Expected delay < 5 mins
For further info: Actavo for Virgin Media
_______________________________________________
Lower Park Lane, Parkside, Rossett Water Network Repairs
2 way traffic lights
From 19/05/2017 to 23/05/2017 Duration 5 days Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
Hazel Grove, Wrexham Gas Main Replacement
ROAD CLOSURE
From 19/05/2017 to 01/06/2017 Duration 2 weeks Expected delay N/A
For further info: Western Gas Alliance
_______________________________________________
Brymbo Link Road, Tan-y-fron Tree Maintenance
2 way traffic lights
From 22/05/2017 to 22/05/2017 Duration 1 day Expected delay < 5 mins
For further info: WCBC 01978 298989
_______________________________________________
B5097 Church Street jct. Cemetery Road, Rhosllanerchrugog BT Cabling/ Ducting
3 way traffic lights
From 22/05/2017 to 22/05/2017 Duration 1 day Expected delay < 5 mins
For further info: BT – 08450 047105
Be Aware: 09:30 – 15:30hrs
_______________________________________________
Middle Road, Sontley BT Cabling/ Ducting
ROAD CLOSURE
From 25/05/2017 to 27/05/2017 Duration 3 days Expected delay N/A
For further info: GCN Ltd 01745 331551
_______________________________________________
A528 Overton Road, Marchwiel BT Cabling/ Ducting
2 way traffic lights
From 23/05/2017 to 25/05/2017 Duration 3 days Expected delay < 5 mins
For further info: GCN Ltd 01745 331551
Be Aware: 09:30 – 15:30
_______________________________________________
Smithy Lane, Wrexham Virgin Media – Cabling Works
2 way traffic lights
From 24/05/2017 to 26/05/2017 Duration 3 days Expected delay < 5 mins
For further info: Actavo for Virgin Media
_______________________________________________
B5430 Old Road, Minera Water Network Repairs
2 way traffic lights
From 25/05/2017 to 30/05/2017 Duration 6 days Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
A5152 Chester Road jct.Ty Gwyn Lane, Wrexham Virgin Media – Cabling Works
3 way traffic lights
From 20/05/2017 to 21/05/2017 Duration 2 days Expected delay < 5 mins
For further info: Actavo for Virgin Media
_______________________________________________
Jeffreys Road, Wrexham Gas Main Replacement
3 way traffic lights
From 22/05/2017 to 19/06/2017 Duration 4 weeks Expected delay < 5 mins
For further info: Wales and West Utilities 01792 326214
_______________________________________________
B5130 Holt Road jct. Bedwell Road, Cross Lanes BT Openreach – Network Repairs
3 way traffic lights
From 21/05/2017 to 21/05/2017 Duration 1 day Expected delay < 5 mins
For further info: BT – 08450 047105
_______________________________________________
Striga Bank jct.Striga Lane, Hanmer Lay new water main
3 way traffic lights
From 22/05/2017 to 07/07/2017 Duration 6 weeks Expected delay < 5 mins
For further info: Dee Valley Water 01978 846946
_______________________________________________
A5 Froncysyllte Wall Repairs
2 way traffic lights
From 22/05/2017 to 26/05/2017 Duration 5 days Expected delay < 5 mins
For further info: A. Parry Construction Co. Ltd.
_______________________________________________
B5605 Bridge Street, Ruabon Tree Maintenance
Stop & Go
From 23/05/2017 to 23/05/2017 Duration 1 day Expected delay < 5 mins
For further info: WCBC 01978 298989
Be Aware: 09:30 – 15:30
_______________________________________________
Oxford Street, Cefn Mawr Carriageway maintenance
3 way traffic lights
From 22/05/2017 to 02/06/2017 Duration 2 weeks Expected delay at Peak times
For further info: Roadway Civil Engineering & Surfacing Ltd.
_______________________________________________