Does anyone know when the works to upgrade the Wrexham-Chester railway line are going to be finished?
It was supposed to be finished by last November (http://www.olddailypostlink.co.uk/news/north-wales-news/wrexham-chester-40-million-rail-10405429), then various dates have been floated about with the most recent one I heard being the end of July 2016 but they still don’t seem to be completed.
The new track is laid, signals have been put up, the level crossings have the vehicle detectors installed and have had new barrier machines/lights (although they aren’t being used). What’s holding it up now?